The scheduling interface facilities



   The media plan copying from one day, in the Weekly or per Week types:
1. Select the desired day of the week from the Weekly column
2. Notice that in the label from the first column the name of the day appears
3. Schedule the desired hour or time intervals and select by clicking the label from the first column with the current day name
4.  The label takes the form of a pushed butto
5. Move the mouse over the other days of the Weekly column and click on the day where you want the current schedule copied automatically

    To copy the "per-Week" structures, the same mechanism is used, with a few modifications:
1. In the Weekly column presented above, one week from the contract will be shown
2. To copy a weekly media-plan, the week from the first step will be selected and after that, the week that we wish to schedule with the existing scheme.